In September 2008, DFR Kwakudi was commissioned by LDM Consortium and Coega Development Corporation to undertake a comprehensive Engineering Survey of the electrical installations at Dietrich Primary School. This important project aimed to ensure that the school's electrical system met current demands and could accommodate future growth.


Scope of Work:

The key tasks for DFR Kwakudi in this project included:

  • Inspection of Existing Electrical Installations: Our team thoroughly examined the school’s current electrical system to assess its functionality.

  • Evaluation for Future Expansion: We evaluated whether the existing system could handle additional load demands that might arise from potential future extensions to the school.

  • Collaboration with the School: Through attending mandatory briefing meetings, we worked closely with the school’s administration to understand their specific requirements and ensure their electrical needs were met.


Project Completion:

  • Timeline: Completed in 2015

  • Project Value: R17 million


This project not only ensured the safety and efficiency of the school's electrical infrastructure but also prepared it for any future developments. The successful completion highlights DFR Kwakudi’s commitment to quality and professional consulting services.